REPORTE INICIAL | | | | | | | |
REVISIÓN DE PLANERÍA, INSTALACIONES Y EQUIPAMIENTO | | | | | | | |
CONTRATO CFE | | | 4/11/2024 | 21/11/2024 | | | |
PEGUE DE MUROS NIVEL 2 | | | 24/2/2025 | 12/3/2025 | | | |
RANURAS INSTALACIONES | | | 20/3/2025 | 29/3/2025 | | | |
COLADO CASTILLOS NIVEL 2 | | | 22/3/2025 | 29/3/2025 | | | |
ENJARRES INTERIORES | | | 31/3/2025 | 16/4/2025 | | | |
HABILITADO DE ACERO NIVEL 2 | | | 1/4/2025 | 8/4/2025 | | | |
DALA DE CERRAMIENTO NIVEL 2 | | | 1/4/2025 | 5/4/2025 | | | |
MURO DE ENRACE NIVEL 2 | | | 7/4/2025 | 14/4/2025 | | | |
CIMBRADO NIVEL 2 | | | 15/4/2025 | 24/4/2025 | | | |
ARMADO DE LOSA NIVEL 2 | | | 25/4/2025 | 7/5/2025 | | | |
INSTALACIONES LOSA NIVEL 2 | | | 8/5/2025 | 15/5/2025 | | | |
ENCACHETADO, CASETON, MALLA ELECTROSOLDADA NIVEL 2 | | | 16/5/2025 | 21/5/2025 | | | |
COLADO LOSA NIVEL 2 | | | 22/5/2025 | 24/5/2025 | | | |
PEGUE DE MUROS NIVEL 3 | | | 27/5/2025 | 12/6/2025 | | | |
DESCIMBRADO NIVEL 2 | | | 13/6/2025 | 21/6/2025 | | | |
COLADO CASTILLOS NIVEL 3 | | | 23/6/2025 | 30/6/2025 | | | |
RANURAS INSTALACIONES NIVEL 2 | | | 23/6/2025 | 1/7/2025 | | | |
ENJARRES INTERIORES NIVEL 2 | | | 2/7/2025 | 19/7/2025 | | | |